Course report Sept 23rd 2019
It’s been a difficult summer greenkeeping wise due to the high level of growth on all areas of the course and practice area. Routinely we cut things such as tee and bunker banks, semi-roughs, range etc on a fortnightly cycle but this year has seen us struggle to keep up on these jobs as everything is needing done more often and more grass equals more time to do each job. The range has been particularly difficult to keep on top of (with a weekly cut) resulting in a lot of smaller jobs just not getting done.
Rainfall in August measured 106mm and that is approx. 3 x more than a normal summer month. Nonetheless the greens have performed very well and the fairways continue to improve with the wet weather.
Greens
Little work on the greens this summer apart from cutting and occasional rolling. Two wetter/seaweed/potassium carbonate sprays with a little Nitrogen have gone on June and July just to tick things along. A verti-cut last week and another seaweed/calcium/iron spray to try and dry up a little Fusarium marking here and there. The top putting green was hollow tined and Graden scarified (Mon 16th Sept) with some bent grass seed introduced. Recovery has been pretty quick due to the weather of late. This week we will be solid spiking and following up with the scarifier/seed (bent seed at 5g/m2) and top dressing. A wet start today slowed things down but 12 greens spiked and 5 greens scarified/seeded. Rolling to re-enstate surfaces and keeping an eye on moisture levels for recovery and enhancing seed germination.

Going into the autumn I would like to carry out some slitting then late autumn (late Nov) the greens will need another hollow tine with 6mm tines and also a deep verti-drain with larger 3/4” tines during December. All this work will enhance drainage and surface firmness, promote deeper root growth and help combat fairy ring. In turn they will become more resilient for next year.
Roughs
Majority of tall roughs cut and collected and will be sprayed with Laser to reduce course grasses within.
Semis
All semi roughs were sprayed with herbicide to treat Plantains and clover
Tees
Some tees have been spiked/sanded and seeded
Pro shop/office work – site prep work (Oct 14th)
- The area of the yellow/red tee where the putting green is to be extended needs stripping back first + RHS of this tee. (Approx 6-7m)
- Re locate RHS tee sprinkler.
- Strip turf in front of Medal tee approx 6-8m and lay aside.
- PG extension area then needs to be excavated and contoured to desired putting green level with sand amended through the soil. De stone. (require mini digger)
- Stock pile soil front medal tee.
- Lift turf from car park end of putting green and re lay onto new extension. Lay apron turf as required and excess turf below 1st hole whin carry.
- Enlarge and raise medal tee and re turf
Removal of the dust path to the left of the yellow tee at 6th and some of the turf lifted from the putting green side could be used here.







All 90mm MDPE ring main pipe and 63mm going to the greens and tees were vibratory mole ploughed into the ground to 600mm deep. The soil underneath is very stoney to say the least and several sections of the old original 1″ steel irrigation line got unearthed. During March all the 50mm pipe and Valve in head sprinklers were installed around the greens and positioned a little further out so that the aprons can receive irrigation also. Recently the tees sprinklers have been going in and all our old greens sprinklers have been re used to save some money. These are being set in down either side of the tees to allow accurate watering of the tees themselves and also taking account of heavily walked areas by the tees. At this date there are still 5 tees and the lower putting green to complete, the new tank to erect and a new variable speed pump to go into the pumphouse. All going well once electrical and softwear work is tested, the pipe lines and sprinklers flushed and primed we are looking at around a mid April completion.











Pot seeding of all greens took place on September 10th – 12th. 160kg (17 grammes/m2) of Bar Fescue seed was broadcast over the open tine holes created by our versatile SL6 Wiedenmann machine with solid 16mm tines set into the turf about 30 – 40mm deep. A heavy sanding of around 15 tonnes in total went on first and when it had dried enough it was all drag matted back into the tine holes. Further brushing and rolling took place to help fill up the holes and restore the greens for play.





13.5 bags were used over the 20 greens and this provided 17kg N and K/Ha. This is intended to last for around 7 to 8 weeks to which point liquid feeds will take over as we enter into the hotter summer months. The greens will be slightly slower for a few days until the feed has fully broken down into the grass sward.
We have removed the centre fairway pot bunker and created a swale in its place. In addition to this a new right hand side fairway bunker has been created some 35 yards past the first one. The reasoning behind this is to reward a good drive that holds the fairway in a prevailing westerly wind and in turn tighten up the landing area for the longer hitters. The depth has been kept fairly shallow to offer a longish recovery shot should you go for it. 







